system-config/modules/releasestatus/files/integrated.yaml
Thierry Carrez 21122a1343 Switch release status tracking to Kilo
Specify dates and projects for the Kilo cycle and switch
status.o.o/release to track that instead of Juno.

Change-Id: I0a07ad03a7459fc9256fde45016cd5de6c324ff5
2014-11-13 12:00:33 +01:00

37 lines
860 B
YAML

# Name of the series
series: kilo
# Final release date
releasedate: 2015-04-30
# Short milestone codes, with number of weeks leading to them, not including
# the milestone week. The last one should be the release date.
#
# For example, Juno cycle schedule:
# https://wiki.openstack.org/wiki/Juno_Release_Schedule
# [6, j1] - taking in account pre-summit weeks (not including j1 week)
# [5, j2] - 5 full weeks between j1 and j2 (not including j1 or j2 weeks)
# [5, j3] - 5 full weeks between j2 and j3 (not including j2 or j3 weeks)
# [5, Oct 16] - 5 weeks for rc and release, not including release week
milestones:
- [7, k1]
- [6, k2]
- [5, k3]
- [5, Apr 30]
# Set of projects to consider in the report
products:
- nova
- glance
- swift
- keystone
- horizon
- neutron
- cinder
- oslo-incubator
- ceilometer
- heat
- trove
- sahara
- ironic