2023 CFN Release Timeline
Event | Dates | Relative Dates | Start Relative Dates | Description |
---|---|---|---|---|
Release Start | July 27 | Start date | Start date | Declare Intention: Each sub-project should create or update sub-group introduction and release plan. |
Initial Checkpoint | Aug. 10 | Start date + 2 weeks | Start date + 2 weeks | Release plan review. |
Middle Checkpoint | Sept. 28 | Initial checkpoint + 7 weeks | Start date + 9 weeks | Progress chack. |
Code Freeze | Oct. 26 | Middle checkpoint + 4 weeks | Start date + 13 weeks | Cut and lock release branch. Any update of code after this day will NOT be included within current release. |
Final Checkpoint | Nov. 9 | Code freeze + 2 weeks | Start date + 15 weeks | Each project finish related documentation and release summry for release review. |
Fornal Release | Nov. 16 | Final checkpoint + 1 week | Start date + 16 weeks | Formal release with release tag. |