# 2023 CFN Release Timeline
|
|
|
|
| Event |Dates |Relative Dates |Start Relative Dates |Description |
|
|
| :--- | :--- | :--- | :--- | :--- |
|
|
| Release Start |July 27 |Start date |Start date |Declare Intention: Each sub-project should create or update sub-group introduction and release plan. |
|
|
| Initial Checkpoint |Aug. 10 |Start date + 2 weeks |Start date + 2 weeks |Release plan review. |
|
|
| Middle Checkpoint |Sept. 28 |Initial checkpoint + 7 weeks |Start date + 9 weeks |Progress chack. |
|
|
| Code Freeze |Oct. 26 |Middle checkpoint + 4 weeks |Start date + 13 weeks |Cut and lock release branch. Any update of code after this day will NOT be included within current release. |
|
|
| Final Checkpoint |Nov. 9 |Code freeze + 2 weeks |Start date + 15 weeks |Each project finish related documentation and release summry for release review. |
|
|
| Fornal Release |Nov. 16 |Final checkpoint + 1 week |Start date + 16 weeks |Formal release with release tag. | |